CONSTRUCTION UPDATES - April 2014

 
Column Concreting Of 15th Floor In Progress

VIEW: TOWER (A)
Progress: Column Concreting Of 15th Floor In Progress

Column Concreting Of 17th Floor In Progress

VIEW: TOWER (B)
Progress: Column Concreting Of 17th Floor In Progress

Concreting Of 12th Floor Roof Slab In Progress

VIEW: TOWER (C)
Progress: Concreting Of 12th Floor Roof Slab In Progress

     
Shuttering & Reinforcement Laying Of 15th Floor Roof In Progress

VIEW: TOWER (D)
Progress: Shuttering & Reinforcement Laying Of 15th Floor Roof In Progress

Concreting Of 17th Floor Roof Slab In Progress

VIEW: TOWER (E)
Progress: Concreting Of 17th Floor Roof Slab In Progress

Shuttering & Reinforcement Laying Of 17th Floor Roof In Progress

VIEW: TOWER (F)
Progress: Shuttering & Reinforcement Laying Of 17th Floor Roof In Progress

     
Concreting Of 18th Floor Roof Slab In Progress

VIEW: TOWER (G)
Progress: Concreting Of 18th Floor Roof Slab In Progress

Column & Shear Wall Concreting Of Basement In Progress

VIEW: TOWER (EWS)
Progress: Column & Shear Wall Concreting Of Basement In Progress

 