CONSTRUCTION UPDATES - February 2016

 
STRUCTURE & PLASTER WORK COMPLETED

VIEW: TOWER (A)
Progress: Structure & Plaster Work Completed, Finishing & Services Work Is In Progess

SERVICES WORK IS IN PROGESS

VIEW: TOWER (B)
Progress: Structure & Plaster Work Completed, Finishing & Services Work Is In Progess

STRUCTURE & PLASTER WORK COMPLETED, FINISHING

VIEW: TOWER (C)
Progress: Structure & Plaster Work Completed, Finishing & Services Work Is In Progess

     
STRUCTURE & PLASTER WORK COMPLETED, FINISHING

VIEW: TOWER (D)
Progress: Structure & Plaster Work Completed, Finishing & Services Work Is In Progess

BRICK WORK, PLASTER WORK, FINISHING & SERVICES WORK IS IN PROGESS

VIEW: TOWER (E)
Progress: Structure Work Completed. Brick Work, Plaster Work, Finishing & Services Work Is In Progess

STRUCTURE & PLASTER WORK COMPLETED, FINISHING

VIEW: TOWER (F)
Progress: Structure & Plaster Work Completed, Finishing & Services Work Is In Progess

     
STRUCTURE & PLASTER WORK COMPLETED, FINISHING

VIEW: TOWER (G)
Progress: Structure & Plaster Work Completed, Finishing & Services Work Is In Progess

SLAB CASTING OF 5TH FLOOR COMPLETED

VIEW: TOWER (EWS)
Progress: Slab Casting Of 5th Floor Completed

COLUMN CONCRETING OF TERRACE IN PROGRESS

VIEW: MULTI PURPOSE HALL
Progress: Column Concreting Of Terrace In Progress

     
SHUTTERING WORK OF TERRACE SLAB IN PROGRESS

VIEW: HEALTH CLUB
Progress: Shuttering Work Of Terrace Slab In Progress

EXTERNAL & INTERNAL PLASTER IN PROGRESS

VIEW: E.S.S.
Progress: External & Internal Plaster In Progress

 

 

     